rbi.page.title.1
rbi.page.title.2
83772752
പ്രസിദ്ധീകരിച്ചത് സെപ്റ്റംബർ 18, 2020
Table 36 : Sector-Wise Cost Overrun of Delayed Central Sector Projects
(₹ Crores) | |||||||||||||||
Sector / Year | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
1. Atomic energy | |||||||||||||||
a) Number of projects | 1 | 1 | 3 | 3 | 3 | 3 | 4 | 3 | 4 | 4 | 4 | 4 | 4 | 4 | 4 |
b) Original estimate | 343 | 343 | 16586 | 20456 | 20876 | 17769 | 38056 | 36950 | 40442 | 40442 | 40442 | 40442 | 67120 | 67120 | 67120 |
c) Now anticipated | 343 | 343 | 16586 | 19525 | 22130 | 22607 | 40709 | 41049 | 46726 | 51918 | 51918 | 52241 | 69728 | 75589 | 80300 |
d) Cost overrun | 0 | 0 | 0 | -931 | 1254 | 4838 | 2700 | 4100 | 6284 | 11476 | 11476 | 11799 | 2608 | 8469 | 13180 |
2. Civil aviation | |||||||||||||||
a) Number of projects | 1 | 1 | 0 | 2 | 7 | 3 | 3 | 3 | 3 | 5 | 1 | 3 | 1 | 1 | 4 |
b) Original estimate | 192 | 192 | 0 | 246 | 2823 | 2420 | 2588 | 2588 | 989 | 1659 | 309 | 842 | 315 | 315 | 3235 |
c) Now anticipated | 192 | 192 | 0 | 246 | 2823 | 2420 | 2970 | 2970 | 1042 | 1712 | 309 | 1239 | 441 | 441 | 3362 |
d) Cost overrun | 0 | 0 | 0 | 0 | 0 | 0 | 400 | 400 | 53 | 53 | 0 | 397 | 127 | 127 | 127 |
3. Coal | |||||||||||||||
a) Number of projects | 1 | 1 | 1 | 8 | 24 | 10 | 19 | 28 | 30 | 37 | 42 | 35 | 37 | 37 | 41 |
b) Original estimate | 200 | 200 | 287 | 6751 | 12689 | 5851 | 13791 | 24263 | 26241 | 28302 | 23987 | 19120 | 20254 | 21142 | 23505 |
c) Now anticipated | 183 | 183 | 287 | 8366 | 13962 | 7541 | 15102 | 26137 | 36435 | 32310 | 25308 | 19022 | 20473 | 22274 | 28853 |
d) Cost overrun | -17 | -17 | 0 | 1615 | 1273 | 1690 | 1300 | 1900 | 10194 | 4008 | 1322 | -98 | 219 | 1133 | 5348 |
4. Finance | |||||||||||||||
a) Number of projects | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
b) Original estimate | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
c) Now anticipated | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
d) Cost overrun | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
5. Fertilisers | |||||||||||||||
a) Number of projects | 0 | 0 | 0 | 0 | 0 | 1 | 2 | 1 | 0 | 0 | 0 | 1 | 2 | 1 | 4 |
b) Original estimate | 0 | 0 | 0 | 0 | 0 | 1479 | 763 | 1479 | 0 | 0 | 0 | 198 | 681 | 198 | 1101 |
c) Now anticipated | 0 | 0 | 0 | 0 | 0 | 1479 | 763 | 1479 | 0 | 0 | 0 | 209 | 692 | 209 | 1101 |
d) Cost overrun | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 12 | 12 | 12 | 0 |
6. Mines | |||||||||||||||
a) Number of projects | 0 | 0 | 0 | 0 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 2 |
b) Original estimate | 0 | 0 | 0 | 0 | 4092 | 4092 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 5707 |
c) Now anticipated | 0 | 0 | 0 | 0 | 4092 | 4402 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 5703 |
d) Cost overrun | 0 | 0 | 0 | 0 | 0 | 310 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | -3 |
7. Steel | |||||||||||||||
a) Number of projects | 4 | 6 | 7 | 14 | 20 | 7 | 10 | 15 | 13 | 17 | 15 | 19 | 15 | 10 | 7 |
b) Original estimate | 773 | 1609 | 10268 | 22732 | 39430 | 30280 | 51099 | 64698 | 64208 | 56371 | 39095 | 41294 | 46113 | 26774 | 22838 |
c) Now anticipated | 773 | 1678 | 10273 | 27111 | 46120 | 39780 | 57158 | 70856 | 70162 | 59940 | 39601 | 41521 | 45901 | 33578 | 30095 |
d) Cost overrun | 0 | 69 | 5 | 4379 | 6690 | 9500 | 6100 | 6200 | 5954 | 3569 | 505 | 227 | -213 | 6804 | 7257 |
8. Petro-chemicals | |||||||||||||||
a) Number of projects | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 1 | 0 | 0 | 0 | 0 | 0 |
b) Original estimate | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 5461 | 0 | 5461 | 0 | 0 | 0 | 0 | 0 |
c) Now anticipated | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 8920 | 0 | 9834 | 0 | 0 | 0 | 0 | 0 |
d) Cost overrun | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 3500 | 0 | 4373 | 0 | 0 | 0 | 0 | 0 |
9. Petroleum | |||||||||||||||
a) Number of projects | 13 | 24 | 20 | 26 | 41 | 27 | 38 | 39 | 50 | 43 | 38 | 35 | 27 | 39 | 52 |
b) Original estimate | 24085 | 35560 | 29457 | 46429 | 86400 | 37562 | 107198 | 111743 | 139493 | 88533 | 47995 | 52021 | 52801 | 97368 | 121051 |
c) Now anticipated | 29692 | 45525 | 36871 | 56635 | 111051 | 40105 | 115427 | 121838 | 153759 | 101635 | 49999 | 52088 | 56325 | 102310 | 132765 |
d) Cost overrun | 5607 | 9965 | 7414 | 10206 | 24651 | 2542 | 8200 | 10100 | 14265 | 13102 | 2004 | 68 | 3524 | 4942 | 11713 |
(Continued) |
TABLE 36 : SECTOR-WISE COST OVERRUN OF DELAYED CENTRAL SECTOR PROJECTS (End-March) (Concld.) | |||||||||||||||
(₹ Crores) | |||||||||||||||
Sector / Year | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
10. Power | |||||||||||||||
a) Number of projects | 20 | 12 | 28 | 28 | 33 | 40 | 50 | 53 | 44 | 63 | 64 | 57 | 62 | 51 | 40 |
b) Original estimate | 18900 | 26973 | 52213 | 68600 | 82771 | 105569 | 137766 | 135656 | 124490 | 164942 | 171622 | 199226 | 227593 | 199221 | 192924 |
c) Now anticipated | 28220 | 27903 | 54332 | 72140 | 86254 | 110220 | 152267 | 150492 | 142172 | 193266 | 208830 | 230151 | 274184 | 244605 | 262443 |
d) Cost overrun | 9320 | 930 | 2119 | 3540 | 3483 | 4631 | 14500 | 14800 | 17681 | 28323 | 37208 | 30925 | 46590 | 45384 | 69519 |
11. Railways | |||||||||||||||
a) Number of projects | 19 | 19 | 22 | 44 | 53 | 31 | 34 | 41 | 37 | 35 | 31 | 38 | 29 | 97 | 144 |
b) Original estimate | 8992 | 8952 | 9758 | 15871 | 19388 | 22532 | 23671 | 27924 | 28589 | 29092 | 36714 | 41534 | 39411 | 123380 | 185666 |
c) Now anticipated | 17296 | 17823 | 21085 | 40072 | 40523 | 43774 | 56068 | 73537 | 73022 | 86253 | 90432 | 109806 | 110498 | 201546 | 280915 |
d) Cost overrun | 8305 | 8871 | 11327 | 24201 | 21135 | 21242 | 32400 | 45600 | 44432 | 57160 | 53718 | 68273 | 71087 | 78166 | 95249 |
12. Surface transport | |||||||||||||||
a) Number of projects | 65 | 82 | 131 | 139 | 143 | 109 | 93 | 95 | 23 | 104 | 128 | 107 | 48 | 111 | 180 |
b) Original estimate | 18244 | 22712 | 34972 | 40007 | 48532 | 39092 | 40272 | 54950 | 8843 | 77042 | 88402 | 85274 | 34466 | 96854 | 136250 |
c) Now anticipated | 18360 | 23404 | 35789 | 40643 | 48946 | 40490 | 43172 | 58195 | 11095 | 78983 | 90842 | 90139 | 36987 | 99476 | 188870 |
d) Cost overrun | 116 | 692 | 817 | 637 | 414 | 1399 | 2900 | 3250 | 2253 | 1941 | 2440 | 4865 | 2522 | 2622 | 52620 |
13. Telecommunication | |||||||||||||||
a) Number of projects | 21 | 23 | 18 | 22 | 35 | 35 | 9 | 5 | 4 | 2 | 2 | 2 | 2 | 3 | 2 |
b) Original estimate | 6026 | 7978 | 7153 | 7513 | 14069 | 16628 | 3856 | 2935 | 2018 | 721 | 15445 | 15445 | 13752 | 13781 | 13566 |
c) Now anticipated | 5563 | 7399 | 7177 | 6947 | 14391 | 17139 | 4035 | 2761 | 1843 | 721 | 15345 | 15345 | 25082 | 25118 | 24904 |
d) Cost overrun | -463 | -579 | 24 | -566 | 322 | 511 | 200 | -174 | -175 | 0 | -100 | -100 | 11330 | 11337 | 11338 |
14. Others | |||||||||||||||
a) Number of projects | 4 | 2 | 1 | 1 | 6 | 4 | 2 | 1 | 1 | 17 | 18 | 26 | 27 | 27 | 67 |
b) Original estimate | 5544 | 614 | 543 | 543 | 9111 | 15728 | 6938 | 6395 | 2494 | 82662 | 64808 | 98854 | 86365 | 71272 | 99873 |
c) Now anticipated | 12332 | 1492 | 1187 | 1187 | 10315 | 31872 | 12796 | 11609 | 2494 | 82662 | 72118 | 108617 | 87106 | 72514 | 101877 |
d) Cost overrun | 6788 | 878 | 644 | 644 | 1204 | 16144 | 5858 | 5214 | 0 | 0 | 7310 | 9763 | 742 | 1242 | 2004 |
Total | |||||||||||||||
a) Number of projects | 149 | 171 | 231 | 287 | 366 | 271 | 264 | 285 | 209 | 328 | 343 | 327 | 254 | 381 | 547 |
b) Original estimate | 83299 | 105133 | 161237 | 229148 | 340181 | 299002 | 425998 | 475042 | 437807 | 575227 | 528819 | 594250 | 588870 | 717425 | 872836 |
c) Now anticipated | 112954 | 125941 | 183587 | 272872 | 400607 | 361829 | 500467 | 569843 | 538750 | 699234 | 644702 | 720378 | 727418 | 877661 | 1141187 |
d) Cost overrun | 29655 | 20808 | 22351 | 43724 | 60426 | 62827 | 74469 | 94801 | 100943 | 124007 | 115883 | 126128 | 138548 | 160236 | 268351 |
Notes : 1. Data relate to central sector projects costing ₹100 Crore and above up to 2010. From 2011 onwards data pertain to projects costing ₹150 Cr and above. 2. Projects without date of commissioning are not considered. 3. Cost overrun is taken as the difference between the 'anticipated cost' and the 'original cost'. 4. Surface transport = Road transport + Shipping & ports. 5. Others = Heavy Industry+ Defence Production + Health & family welfare + Urban Development. Source : Ministry of Statistics and Programme Implementation, Government of India. |
प्ले हो रहा है
കേൾക്കുക
പേജ് അവസാനം അപ്ഡേറ്റ് ചെയ്തത്:
ഈ പേജ് സഹായകരമായിരുന്നോ?