Table 37 : Sector-wise Cost Overrun of Delayed Central Sector Projects
(Rupees crore)
Sector
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005 P
1
2
3
4
5
6
7
8
9
10
11
12
1.
Atomic energy
a)
Number of projects
7
6
5
5
3
3
0
0
1
0
0
b)
Original estimate
3020.7
2638.2
2439.3
2455.6
1937.8
1937.8
0
0
3447.1
0
0
c)
Now anticipated
6464.8
5004.0
4904.0
5041.3
5713.7
5713.7
0
0
6760.0
0
0
d)
Cost overrun
3444.0
2365.7
2464.6
2585.7
3775.9
3775.9
0
0
3312.9
0
0
2.
Civil aviation
a)
Number of projects
1
3
3
2
2
0
0
0
0
0
0
b)
Original estimate
210.0
1431.8
1431.8
294.1
294.1
0
0
0
0
0
0
c)
Now anticipated
351.9
1667.1
1703.9
566.2
566.2
0
0
0
0
0
0
d)
Cost overrun
141.9
235.3
272.1
272.1
272.1
0
0
0
0
0
0
3.
Coal
a)
Number of projects
5
11
13
15
16
15
8
3
3
2
1
b)
Original estimate
705.8
2935.9
4060.1
6279.9
8320.8
7191.9
5356.2
1975.0
1975.0
384.4
199.9
c)
Now anticipated
1505.2
5075.7
6207.5
7722.7
9925.1
8686.2
6348.2
2010.3
1992.5
569.0
182.6
d)
Cost overrun
799.4
2139.8
2147.4
1442.8
1604.3
1494.3
992.0
35.3
17.5
184.6
-17.3
4.
Finance
a)
Number of projects
1
1
1
1
1
1
1
0
0
0
0
b)
Original estimate
118.3
118.3
118.3
118.3
118.3
118.3
118.3
0
0
0
0
c)
Now anticipated
348.8
348.8
348.8
348.8
348.8
348.8
301.8
0
0
0
0
d)
Cost overrun
230.5
230.5
230.5
230.5
230.5
230.5
183.5
0
0
0
0
5.
Fertilisers
a)
Number of projects
2
3
3
1
0
0
0
1
1
1
1
b)
Original estimate
1578.4
2565.7
2093.2
618.4
0
0
0
350.0
350.0
350.0
350.0
c)
Now anticipated
1578.4
2565.7
2195.4
642.4
0
0
0
509.4
509.4
509.4
610.2
d)
Cost overrun
0
0
102.2
23.9
0
0
0
159.4
159.4
159.4
260.2
6.
Mines
a)
Number of projects
0
0
0
0
0
1
1
1
1
1
0
b)
Original estimate
0
0
0
0
0
157.5
157.5
2062.0
2062.0
2062.0
0
c)
Now anticipated
0
0
0
0
0
157.5
183.6
2062.0
2062.0
2062.0
0
d)
Cost overrun
0
0
0
0
0
0
26.1
0
0
0
0
7.
Steel
a)
Number of projects
3
2
3
5
4
3
1
1
1
1
1
b)
Original estimate
4243.2
3818.0
5443.8
6511.1
5154.1
2693.1
430.5
430.5
298.7
298.7
107.4
c)
Now anticipated
9427.9
8951.2
11167.9
13498.8
8856.7
3787.7
466.7
450.0
298.7
298.7
170.4
d)
Cost overrun
5184.7
5133.2
5724.2
6987.7
3702.6
1094.6
36.2
19.5
0
0
63.0
8.
Petro-chemicals
a)
Number of projects
0
2
3
3
1
1
0
0
0
0
0
b)
Original estimate
0
336.4
3820.7
3820.7
3484.4
3484.4
0
0
0
0
0
c)
Now anticipated
0
336.4
3841.4
3852.6
3809.0
3809.0
0
0
0
0
0
d)
Cost overrun
0
0
20.6
31.8
324.6
324.6
0
0
0
0
0
9.
Petroleum
a)
Number of projects
11
10
13
17
22
17
1
4
8
12
13
b)
Original estimate
9669.9
7594.3
16602.1
18890.6
20238.6
15905.4
133.6
2702.7
9948.3
13652.3
15982.2
c)
Now anticipated
11892.0
9941.9
18169.4
20715.9
22058.1
16899.1
118.1
2624.7
11030.1
15009.7
19358.4
d)
Cost overrun
2222.1
2347.6
1567.4
1825.3
1819.5
993.7
-15.5
-78.0
1081.8
1357.4
3376.2
(Continued)
(Rupees crore)
Sector
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005 P
1
2
3
4
5
6
7
8
9
10
11
12
10.
Power
a)
Number of projects
23
23
22
20
19
15
11
12
11
12
15
b)
Original estimate
13717.5
14555.2
14459.6
9710.0
10233.3
9143.9
8670.5
11445.9
9985.1
7872.3
6963.4
c)
Now anticipated
35470.5
30692.6
32023.3
22552.1
23456.5
24646.3
22920.6
28176.9
24005.8
21545.4
16812.2
d)
Cost overrun
21753.0
16137.4
17563.7
12842.1
13223.2
15502.4
14250.1
16731.0
14020.7
13673.1
9848.8
11.
Railways
a)
Number of projects
25
28
37
20
27
27
25
20
24
28
23
b)
Original estimate
4808.6
5012.5
5380.5
3726.1
5254.8
7909.8
7038.9
6690.1
8036.4
9282.4
8634.2
c)
Now anticipated
10766.8
11452.3
11429.6
6322.8
8443.8
12431.6
12171.8
10336.9
12472.1
14042.8
13612.3
d)
Cost overrun
5958.1
6439.8
6049.0
2596.8
3189.0
4521.8
5132.9
3646.8
4435.7
4760.4
4978.1
12.
Surface transport
a)
Number of projects
5
9
16
20
18
17
16
6
44
53
62
b)
Original estimate
925.0
1867.3
2990.4
3666.2
3256.9
3326.4
3078.8
898.3
10656.5
12583.9
16777.2
c)
Now anticipated
1197.6
2359.5
3864.2
5362.0
5216.6
5290.5
5847.7
1809.8
11362.9
13427.4
17044.9
d)
Cost overrun
272.7
492.2
873.7
1695.9
1959.8
1964.1
2768.9
911.5
706.4
843.5
267.7
13.
Telecommunication
a)
Number of projects
0
0
0
2
0
2
1
0
0
1
5
b)
Original estimate
0
0
0
465.6
0
730.8
546.0
0
0
147.0
1600.5
c)
Now anticipated
0
0
0
671.9
0
730.8
546.0
0
0
147.0
1422.9
d)
Cost overrun
0
0
0
206.3
0
0
0
0
0
0
-177.6
14.
Others
a)
Number of projects
0
0
0
0
0
0
0
1
1
1
4
b)
Original estimate
0
0
0
0
0
0
0
4860.0
4860.0
4860.0
5543.8
c)
Now anticipated
0
0
0
0
0
0
0
8800.0
8800.0
10571.0
12332.2
d)
Cost overrun
0
0
0
0
0
0
0
3940.0
3940.0
5711.0
6788.4
Total
a)
Number of projects
83
98
119
111
113
102
65
49
95
112
125
b)
Original estimate
38997.4
42873.6
58839.9
56556.6
58293.1
52599.3
25530.3
31414.5
51619.1
51493.0
56158.6
c)
Now anticipated
79003.9
78395.1
95855.3
87297.5
88394.5
82501.2
48904.5
56780.0
79293.5
92344.3
81546.1
d)
Cost overrun
40006.4
35521.5
37015.4
30740.9
30101.4
29901.9
23374.2
25365.5
27674.4
40851.3
25387.5
P : Provisional. Note : 1. Data relate to central sector projects costing Rs.100 crore and above. 2. Projects without date of commissioning are not considered. 3. Cost overrun is taken as the difference between the 'anticipated cost' and the 'original cost'. Source : Ministry of Statistics and Programme Implementation, Government of India.
RbiTtsCommonUtility
PLAYING
LISTEN
LOADING...
0:062:49
Related Assets
RBI-Install-RBI-Content-Global
RbiSocialMediaUtility
Share this page:
Install the RBI mobile application and get quick access to the latest news!
RbiWasItHelpfulUtility
Page Last Updated on:
Was this page helpful?Thanks!
Would like to give more details?
Thank you for your feedback!Thank you for your feedback!