Table 34 : Implementation Of Central Sector Projects - Status
(Number of projects) | ||||||||||||
Sector | 1995 | 1996 | 1997 | 1998 | 1999 | 2000 | 2001 | 2002 | 2003 | 2004 | ||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | ||
1. | Atomic energy | 7 | 6 | 6 | 6 | 4 | 4 | 1 | 3 | 4 | 6 | |
a) | Ahead | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | 1 | 1 | |
b) | On schedule | 0 | 0 | 0 | 1 | 1 | 0 | 1 | 3 | 2 | 5 | |
c) | Delayed * | 7 | 6 | 5 | 5 | 3 | 3 | 0 | 0 | 1 | 0 | |
d) | Without D.O.C. | 0 | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
2. | Civil aviation | 1 | 3 | 3 | 2 | 2 | 0 | 0 | 0 | 0 | 0 | |
a) | Ahead | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
b) | On schedule | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
c) | Delayed * | 1 | 3 | 3 | 2 | 2 | 0 | 0 | 0 | 0 | 0 | |
d) | Without D.O.C. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
3. | Coal | 29 | 27 | 24 | 23 | 21 | 20 | 14 | 12 | 6 | 6 | |
a) | Ahead | 0 | 0 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
b) | On schedule | 24 | 16 | 9 | 8 | 5 | 5 | 6 | 9 | 3 | 4 | |
c) | Delayed * | 5 | 11 | 13 | 15 | 16 | 15 | 8 | 3 | 3 | 2 | |
d) | Without D.O.C. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
4. | Finance | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | |
a) | Ahead | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
b) | On schedule | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
c) | Delayed * | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | |
d) | Without D.O.C. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
5. | Fertilisers | 5 | 7 | 7 | 3 | 2 | 3 | 3 | 2 | 1 | 1 | |
a) | Ahead | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
b) | On schedule | 2 | 3 | 3 | 1 | 1 | 2 | 2 | 0 | 0 | 0 | |
c) | Delayed * | 2 | 3 | 3 | 1 | 0 | 0 | 0 | 1 | 1 | 1 | |
d) | Without D.O.C. | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | |
6. | Mines | 0 | 0 | 0 | 3 | 3 | 3 | 3 | 2 | 2 | 1 | |
a) | Ahead | 0 | 0 | 0 | 0 | 1 | 1 | 0 | 0 | 0 | 0 | |
b) | On schedule | 0 | 0 | 0 | 3 | 2 | 1 | 2 | 1 | 1 | 0 | |
c) | Delayed * | 0 | 0 | 0 | 0 | 0 | 1 | 1 | 1 | 1 | 1 | |
d) | Without D.O.C. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
7. | Steel | 5 | 7 | 6 | 5 | 4 | 3 | 1 | 1 | 2 | 3 | |
a) | Ahead | 0 | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
b) | On schedule | 2 | 5 | 2 | 0 | 0 | 0 | 0 | 0 | 1 | 2 | |
c) | Delayed * | 3 | 2 | 3 | 5 | 4 | 3 | 1 | 1 | 1 | 1 | |
d) | Without D.O.C. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
8. | Petro-chemicals | 5 | 5 | 3 | 3 | 1 | 1 | 0 | 0 | 0 | 0 | |
a) | Ahead | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
b) | On schedule | 5 | 3 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
c) | Delayed * | 0 | 2 | 3 | 3 | 1 | 1 | 0 | 0 | 0 | 0 | |
d) | Without D.O.C. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
9. | Petroleum | 24 | 23 | 25 | 34 | 29 | 33 | 27 | 30 | 23 | 29 | |
a) | Ahead | 3 | 0 | 4 | 2 | 3 | 2 | 3 | 2 | 3 | 4 | |
b) | On schedule | 10 | 13 | 8 | 15 | 4 | 14 | 19 | 22 | 10 | 13 | |
c) | Delayed * | 11 | 10 | 13 | 17 | 22 | 17 | 1 | 4 | 8 | 12 | |
d) | Without D.O.C. | 0 | 0 | 0 | 0 | 0 | 0 | 4 | 2 | 2 | 0 | |
10. | Power | 35 | 32 | 31 | 33 | 31 | 25 | 25 | 32 | 35 | 41 | |
a) | Ahead | 2 | 3 | 2 | 1 | 4 | 2 | 0 | 1 | 2 | 3 | |
b) | On schedule | 8 | 5 | 5 | 10 | 7 | 7 | 13 | 19 | 22 | 26 | |
c) | Delayed * | 23 | 23 | 22 | 20 | 19 | 15 | 11 | 12 | 11 | 12 | |
d) | Without D.O.C. | 2 | 1 | 2 | 2 | 1 | 1 | 1 | 0 | 0 | 0 | |
11. | Railways | 32 | 46 | 57 | 77 | 74 | 85 | 85 | 93 | 87 | 103 | |
a) | Ahead | 0 | 2 | 2 | 2 | 0 | 2 | 2 | 1 | 0 | 0 | |
b) | On schedule | 6 | 11 | 12 | 9 | 7 | 7 | 5 | 6 | 5 | 6 | |
c) | Delayed * | 25 | 28 | 37 | 20 | 27 | 27 | 25 | 20 | 24 | 28 | |
d) | Without D.O.C. | 1 | 5 | 6 | 46 | 40 | 49 | 53 | 66 | 58 | 69 | |
12. | Surface transport | 9 | 13 | 20 | 22 | 22 | 21 | 22 | 12 | 100 | 90 | |
a) | Ahead | 0 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | 26 | 20 | |
b) | On schedule | 2 | 3 | 4 | 2 | 3 | 4 | 6 | 6 | 30 | 13 | |
c) | Delayed * | 5 | 9 | 16 | 20 | 18 | 17 | 16 | 6 | 44 | 53 | |
d) | Without D.O.C. | 2 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 4 | |
13. | Telecommunication | 1 | 0 | 4 | 3 | 2 | 2 | 2 | 0 | 1 | 2 | |
a) | Ahead | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
b) | On schedule | 1 | 0 | 4 | 1 | 2 | 0 | 1 | 0 | 1 | 1 | |
c) | Delayed * | 0 | 0 | 0 | 2 | 0 | 2 | 1 | 0 | 0 | 1 | |
d) | Without D.O.C. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
14. | Health & family welfare | 0 | 0 | 0 | 0 | 0 | 0 | 2 | 2 | 2 | 2 | |
a) | Ahead | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
b) | On schedule | 0 | 0 | 0 | 0 | 0 | 0 | 2 | 2 | 2 | 2 | |
c) | Delayed * | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
d) | Without D.O.C. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
15. | Urban development | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 1 | 1 | |
a) | Ahead | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
b) | On schedule | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
c) | Delayed * | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 1 | 1 | |
d) | Without D.O.C. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
16. | Others | 0 | 0 | 0 | 1 | 1 | 1 | 1 | 0 | 0 | 1 | |
a) | Ahead | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
b) | On schedule | 0 | 0 | 0 | 1 | 1 | 1 | 1 | 0 | 0 | 1 | |
c) | Delayed * | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
d) | Without D.O.C. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Total | 154 | 170 | 187 | 216 | 197 | 202 | 187 | 190 | 264 | 286 | ||
a) | Ahead | 5 | 5 | 11 | 5 | 9 | 8 | 5 | 4 | 32 | 28 | |
b) | On schedule | 60 | 59 | 47 | 51 | 33 | 41 | 58 | 68 | 77 | 73 | |
c) | Delayed * | 83 | 98 | 119 | 111 | 113 | 102 | 65 | 49 | 95 | 112 | |
d) | Without D.O.C. | 6 | 8 | 10 | 49 | 42 | 51 | 59 | 69 | 60 | 73 | |
D.O.C. Date of Commissioning. * Includes some of the projects for which information about the delay is not available, but they have date of commissioning. Note : 1. Data relate to central sector projects costing Rs.100 crore and above. 2. Delay is considered with reference to anticipated date of commissioning. Source : Ministry of Statistics and Programme Implementation, Government of India. |